The Illinois Department of Transportation has announced that, in addition to the ongoing closure of Illinois 111 at Interstate 270 in Madison County, a full closure of the ramp from westbound I-270 to northbound Illinois 111 was scheduled to begin, weather permitting, on Tuesday, Aug. 26.
This closure is expected to last approximately 14 days as part of the I-270/Illinois 111 interchange reconstruction project.
The posted detour for the ramp closure is as follows:
- Westbound I-270: Take northbound Illinois 157 to westbound Chain of Rocks Road to northbound Illinois 111
- Northbound I-255: Take eastbound I-270 to northbound Illinois 157 to westbound Chain of Rocks Road to northbound Illinois 111
In addition, one other outer ramp will be closed for 14 days at a different time. The specific closure date for this ramp will be announced as the work progresses.
Work on the entire interchange is anticipated to be completed by the end of October.
Motorists should expect delays and are encouraged to use alternate routes during these closures. Drivers are urged to reduce speed, be alert for changing conditions, obey all construction signage, and refrain from using mobile devices while approaching and traveling through the work zone.
For IDOT District 8 updates, follow on the social media platform X at @IDOTDistrict8 or view area construction details on IDOT’s traveler information map on GettingAroundIllinois.com.